Crossing Improvements of Line F-1 Channel at Sycamore Avenue in the City of Newark
The project consists of installation of an additional box culvert adjacent to the existing box culvert.
Schedule: The project began in August 2008 and will extend until October 2008. Property Owners will be notified by the contractor when work is to begin in their area
Work Update: The contractor is working on the west side of Sycamore Avenue and this work is anticipated to extend until mid September at which time they will begin work on the middle and east side of the crossing.
You can expect traffic delays on Sycamore Avenue due to temporary roadway and lane closures when required.
Contact information:
Bill Lepere, Construction Manager
Phone number: (510) 670-5513
e-mail: bill@acpwa.org
back
Crossing Improvements of Line F-1 Channel at Cherry in the City of Newark
The project consists of installation of an additional box culvert adjacent to the existing box culvert.
Schedule: The project began in August 2008 and will extend until October 2008. Property Owners will be notified by the contractor when work is to begin in their area
Work Update: The contractor is working on the west side of Cherry Avenue and this work is anticipated to extend until mid September at which time they will begin work on the middle and east side of the crossing.
You can expect traffic delays on Cherry Avenue due to temporary roadway and lane closures when required
Contact information:
Bill Lepere, Construction Manager
Phone number: (510) 670-5513
e-mail: bill@acpwa.org
back
Restoration of Line F-1 Channel at Filbert Street in the City of Newark
The project consists of channel bank restoration.
Schedule: The project is scheduled to begin in August 2008 and extend until October 2008. Property Owners will be notified by the contractor when work is to begin in their area
Work Update: The work has not begun yet.
Contact information:
Bill Lepere, Construction Manager
Phone number: (510) 670-5513
e-mail: bill@acpwa.org
back
Restoration of Line C between East 14th Street and Mooney Street in Unincorporated Alameda County
The project consists of bank repair and silt removal.
Schedule: The project is scheduled to begin in August 2008 and extend until October 2008. Property Owners will be notified by the contractor when work is to begin in their area
Work Update: The work has not begun yet.
Contact information:
Bill Lepere, Construction Manager
Phone number: (510) 670-5513
e-mail: bill@acpwa.org
back
Restoration of Line A between Cabot Road and Line E in the City of Hayward
The project consists of bank repair and silt removal.
Schedule: The project is scheduled to begin in August 2008 and extend until October 2008. Property Owners will be notified by the contractor when work is to begin in their area
Work Update: The work has not begun yet.
Contact information:
Bill Lepere, Construction Manager
Phone number: (510) 670-5513
e-mail: bill@acpwa.org
back
Restoration of Line F, Peralta Creek in the City of Oakland
The project consists of restoration of the banks of the Peralta Creek between 36th Avenue and Bridge Avenue.
Schedule: The project began in July and will extend until October 2008. Property Owners will be notified by the contractor when work is to begin in their area
Work Update: The contractor has begun slope stabilization on both sides of the creek..
Contact information:
Bill Lepere, Construction Manager
Phone number: (510) 670-5513
e-mail: bill@acpwa.org
back
|